Multiple Choice

A contractor is drafting a $12,000 payment schedule for a residential rewiring project. Their internal breakdown shows the 'Rough-in' phase (labor and materials) is worth $4,000 and the 'Trim/Finish' phase is worth $8,000.

Proposed Schedule:

  • $2,000 due upon signing.
  • $7,000 due upon completion of the Rough-in.
  • $3,000 due upon final inspection.

Which of the following correctly analyzes the conflict between this schedule and guidelines that limit progress payments to the value of completed work?