Multiple Choice

A contractor reclassified a project coordinator’s salary from direct labor to overhead to simplify estimating, but left the overhead markup unchanged. After that change, completed jobs kept showing actual cost above estimate. Which explanation best connects the bookkeeping change to the new gap?