Multiple Choice

A contractor schedules an electrical inspection for a residential generator installation on the same day the gas line is completed. However, the electrical inspector refuses to sign off on the project because the gas line has not yet received its own separate mechanical inspection approval. What analytical failure in the project planning phase led to this delay?