Multiple Choice

A contractor submits a signed proposal for a $4,000 residential service upgrade. Two days later, the homeowner calls and asks to add a 240V outlet for an EV charger. The contractor agrees over the phone to do it for an extra $500 but does not issue a new document. After the job is completed, the homeowner refuses to pay the extra $500, pointing to the original signed document as the only valid agreement.

Analyze this breakdown. Which of the following best identifies the fundamental flaw in the contractor's revision control process?