A Customer Service Representative (CSR) is managing the schedule for an electrical company. The company has one senior technician who is the only person qualified to perform 'Main Panel Upgrades.' This technician is already booked for an upgrade on Tuesday morning. When a new customer requests a panel upgrade for that same Tuesday morning, the CSR books the appointment anyway, reasoning that 'if the technician works 20% faster than usual, we can fit both jobs in.'

Evaluate this decision. Which of the following is the most accurate critique of the CSR's approach to capacity planning?