A job cost report lists two material lines. For "12 AWG copper cable," the estimated quantity is 5, the actual quantity is 5, the estimated unit cost is $62, and the actual unit cost is $71. For "EMT straps," the estimated quantity is 40, the actual quantity is 52, and the unit cost is $0.35 in both columns. Which analysis best explains the two overruns?