A project manager is critiquing the material handling plan for a multi-floor renovation. The logistics team proposes dumping all materials in a single, ground-floor laydown area to simplify delivery drop-offs. The manager rejects this proposal in favor of grouping and staging materials by individual rooms. This critical decision is justified because while a single laydown area makes deliveries easier, staging by work area is necessary to eliminate the crew's ________ time.