A seasoned electrician who recently started their own contracting business shares their current permit and inspection workflow with a mentor for feedback. The workflow includes these four practices:

  1. Logging every permit application date, current approval status, inspection booking, and inspection result in a dedicated project tracking spreadsheet.
  2. Standardizing a 5-business-day lead time for booking inspections across all jobs, regardless of the municipality where the work is being performed.
  3. Contacting the customer 24 hours before each scheduled inspection to confirm site access and readiness.
  4. Scanning and filing all inspection result documents—whether passed or failed—in the digital job file for each project.

The mentor reviews the workflow and warns that one of these practices creates a serious scheduling risk that could lead to missed deadlines and broken promises to customers. Which practice should the mentor flag as the most significant liability?