A vendor submits an invoice for $2,750 for a bulk order of electrical tape. The original purchase order (PO) shows an agreed price of $2,500, but the receiving record confirms that the vendor shipped a higher-grade 'professional series' tape that was not requested. The office manager argues that because the tape is already on-site and 'better' than what was ordered, the contractor should pay the higher price. How should the owner evaluate the validity of this suggestion based on the three-way match process?