Fill in the Blank

After reviewing a bid for an industrial facility, the owner of an electrical contracting business notices the estimator used a generic online price sheet for a custom transformer with a 50-week lead time. The owner evaluates the financial risk and rejects the estimate, determining that the catalog price will likely become stale before the purchase order is issued. To correct this error and safely lock in the project's cost for a stated period, the owner requires the estimator to obtain a formal, written ____ from the distributor before submitting the final bid.