Multiple Choice

An electrical contractor compares two commercial projects: Project A uses mobile procurement software for all field-based material orders, while Project B uses a traditional system where supervisors call wholesalers and the office processes invoices later. Mid-way through the month, Project A's dashboard accurately reflects that the material budget is 80% spent, but Project B's dashboard shows only 30% spent, despite both projects being at the same stage of work. When analyzing the workflows, which relationship explains this reporting discrepancy?