An electrical contractor decides to stop using 'Staged Deliveries' to save $200 in total delivery fees on a large $50,000 project. However, the project experiences a design change mid-way through, resulting in $8,000 of surplus materials that now require a 20% restocking fee to return. Which of the following is the most accurate evaluation of the contractor's decision?