Multiple Choice

An electrical contractor estimates that a commercial wiring job will take 100 labor hours at a burdened rate of 50/hour(totaling$5,000).Tofinishaheadofschedule,thecontractorusesamoreexperiencedcrewthatcompletestheworkinonly80hours,buttheirhigherburdenedrateis50/hour (totaling \$5,000). To finish ahead of schedule, the contractor uses a more experienced crew that completes the work in only 80 hours, but their higher burdened rate is 75/hour (totaling $6,000). The contractor evaluates this as a 'successful' job because the team beat the labor hour estimate by 20%.

How should you evaluate the accuracy of the contractor's conclusion?