Multiple Choice

An electrical contractor finds that the actual cost for materials on a recent project was $2,500, which is $500 more than they had originally estimated. To analyze whether this discrepancy was caused by a recent supplier price increase or by the field crew ordering more materials than the job required, which specific data points should the contractor compare?