An electrical contractor is estimating a high-end office fit-out that features 15 different types of decorative light fittings. Instead of including a physical spare for every single fitting type in the bid, they decide to include a 5% 'rework and breakage' cost allowance and select a supplier with a 24-hour lead time for replacements. Which of the following is the most accurate evaluation of this strategy's business logic?