Fill in the Blank

An electrical contractor is evaluating whether to transition from a manual paper-based purchase order (PO) approval workflow to an automated mobile procurement system. The mobile system has a software fee of $150 per month. The contractor's main bottleneck is field delays: when a foreman is waiting for a PO approval, their idle labor and the delay to the job costs the company $75 per hour. To evaluate whether this technology investment is financially viable, the contractor calculates the break-even point. The decision to implement the mobile approval system is financially justified if it reduces idle field delays by more than ____ hours per month.