True/False

An electrical contractor is setting up the billing schedule for a new commercial project. The contract allows for monthly billing. To ensure they can pay their suppliers using incoming project cash rather than dipping into company reserves, the contractor decides to schedule the pay application submission for the 20th of the month instead of the 1st. True or False: This scheduling decision effectively supports their cash flow goal.