Multiple Choice

An electrical contractor maintains a cash reserve that successfully covers 12 weeks of fixed operating expenses (wages, rent, and insurance). However, as they near the completion of a large six-month commercial project, they find they are unable to pay their final material invoices, despite the project being profitable and all previous invoices being paid by the client. Analyze the following factors to determine which structural flaw in their reserve sizing is the most likely cause of this specific end-of-project crisis.