An electrical contractor notices a troubling trend: while their company-wide bank balance is steadily decreasing, their individual project reports show that every job is performing 'under budget' with high profit margins. An audit reveals that thousands of dollars in supplier invoices for conduit and wire were paid, but these expenses never appeared on any specific project's financial report.

Which of the following best analyzes how the absence of a formal Purchase Order (PO) system caused this specific breakdown in job-cost tracking?