Multiple Choice

An electrical contractor receives a vendor invoice that lists a 'Standard Shop Rate' for conduit instead of the $15.00 unit price previously negotiated. Furthermore, the invoice indicates the materials were dropped off at the vendor's own loading dock for 'will-call' pickup, even though the contractor's crew was waiting for a delivery at a residential construction site. By analyzing the discrepancies between the invoice and the original Purchase Order (PO), which two specification fields provide the primary evidence needed to dispute these errors with the supplier?