Multiple Choice

An electrical contractor reviews the following entries in their monthly complaint log:

  1. 'The technician didn't have the specialized dimmer switch mentioned in the online request and had to leave the site to buy one.'
  2. 'The estimate was $150 off because the estimator didn't realize the ceiling was 20 feet high and required a specialized lift.'
  3. 'The installer was surprised by the outdated circuit breaker panel in my basement, leading to a two-hour delay to find compatible parts.'

Based on an analysis of these patterns, which systemic improvement would most effectively address the root cause to prevent these recurring miscommunication costs?