An electrical contractor reviews the following mid-project data from a work-in-progress report for an active commercial rewiring job:

• Contract value: $150,000 • Costs incurred to date: $95,000 • Revised estimated total cost: $160,000 • Billed to date: $110,000 • Earned revenue (percentage of completion × contract value): $89,063

Based on this data, which conclusion about the project's financial status is best supported?