An electrical contractor submits a progress invoice for $4,500, which consists of $3,000 for completed wiring and $1,500 for 'Anticipated labor' for the upcoming week. The contractor argues that the $1,500 is necessary to secure the crew's availability and ensure no project delays. Evaluate the contractor's argument based on the progress payment value limit.