Analysis of Competing Manufacturing Processes

A company is analyzing two different manufacturing processes, Process X and Process Y, to produce computer chips.

  • Process X uses 4 technicians and 200 kilowatt-hours (kWh) of energy to produce 1,000 chips per day.
  • Process Y uses 5 technicians and 225 kilowatt-hours (kWh) of energy to produce 1,250 chips per day.

Based on the provided data, which process represents the more energy-intensive technology? Explain your reasoning and show the calculation that supports your conclusion.