Multiple Choice

During an inspection, the inspector tells you they do not like how you routed a specific conduit run and issues a rejection, but they do not mention a specific code violation. You respectfully ask them for the code section or approved-plan requirement that the installation violates. By doing this, what are you primarily trying to accomplish?