Fill in the Blank

Scenario: An electrical subcontractor analyzes the root cause of their recurring cash-flow crises on commercial jobs. By mapping out the payment cycle, they realize their invoices are structurally delayed because they must pass through a general contractor's payment chain before ever reaching the property owner. Concluding that waiting until the end of the project to invoice is financially unviable, the subcontractor decides they must submit invoices for portions of the project as the work advan