Sequence Ordering

To improve the accuracy of your financial reporting, you are creating a new internal policy for how your electrical firm calculates 'Earned Revenue.' You want to ensure that buying expensive materials in bulk (like large rolls of wire or switchgear) does not make a project look more 'complete' than it actually is in the field. Arrange the steps below in the correct logical order to construct this 'Adjusted' WIP reporting process.