Fill in the Blank

While auditing a project that significantly overran its material budget, you find that the estimated number of light fixtures and electrical panels perfectly matches the actual installed quantities. However, the project required substantially more cable tray and conduit than originally estimated. Analyzing this discrepancy indicates that the estimator accurately performed the counting portion of the quantity takeoff, but likely made systemic errors during the ___________ of the linear work items.