True/False

You are a new electrical contractor who just secured a $20,000 project. The materials will cost $5,000 and labor will cost $3,000, both of which you must pay this week. However, the customer will not pay the $20,000 invoice until the work is completed in 30 days. Because this project guarantees a $12,000 profit, you do not need to utilize working capital to take on this job.