Multiple Choice

You are building an estimating spreadsheet for a new project and need to enter the labor rate for terminating data cables. You know that one electrician can terminate 16 cables in a standard 8-hour workday. To prevent calculation errors when estimating total labor hours, how should you format and enter this productivity rate?