You are conducting a mid-project review for an industrial motor installation. You analyze the following data from your project management software:

  • Original Bid: $100,000 Revenue | $30,000 Labor Budget | $40,000 Materials Budget | 30% Planned Margin
  • Current Forecast at Completion: $45,000 Labor | $38,000 Materials | 17% Projected Margin

By analyzing the relationship between these cost components, which of the following conclusions accurately explains the project's profit status?