Fill in the Blank

You are evaluating a troubled project where an electrical contractor was forced to tear down newly installed drywall at their own expense because the AHJ had not yet approved the rough-in wiring. Critiquing the project's original timeline to determine the root cause of this costly error, you find that the contractor failed to coordinate with the drywall crew to pause work before the installation stage was covered. To prevent this financial and compliance failure on future jobs, you require the contractor to implement a proactive schedule control known as inspection ____ point planning.