Fill in the Blank

You are evaluating an electrical contractor's project closeout process and discover they rely entirely on a client's verbal agreement during the verification walkthrough to confirm that all minor defects have been corrected. Judging that this informal approach leaves the business highly vulnerable to reopened disputes and delayed invoices, you advise the contractor to mandate that the client must provide a formal, written ____ before the project can be officially closed and the final payment triggered.