Multiple Choice

You are receiving a delivery of 500 feet of PVC conduit for a run under a parking lot. Your Purchase Order (PO) specifically required 'Schedule 80' for heavy-duty protection, but you notice the materials on the truck are labeled 'Schedule 40.' What is the most effective way to apply delivery verification protocols in this situation?