True/False

You are reviewing a branch-circuit wiring estimate prepared by a junior estimator for a new commercial space. The estimator used the square root formula (floor area divided by the number of electrical points) to calculate the average horizontal distance between points, added a standard vertical drop allowance, and finalized the total wire length for the project. When asked, the estimator stated they did not verify this calculation against any manual point-by-point measurements from the blueprints. True or False: You should approve this estimate because the branch circuit average length shortcut guarantees sufficient accuracy for a final bid, rendering manual verification an unnecessary use of estimating time.