Multiple Choice

You are reviewing a home that will include rooftop solar and a battery backup system. A lead technician recommends using a standard, lower-cost panelboard that does not carry the required marking for the intended interconnected power application. Based on a pre-installation marking review, how should you judge that recommendation?