Multiple Choice

You are reviewing an estimate where a contractor calculated exactly 10 home runs for a panel containing 30 total circuits. Upon analysis, you see the panel schedule consists of 21 lighting circuits (20-amp) and 9 motor circuits (30-amp). Why is the contractor’s estimate of 10 home runs analytically flawed?