You are reviewing two different scope descriptions for a residential service call to install a dedicated circuit for a new kiln in a customer's basement.

Option A: 'Install 30-amp circuit for kiln in basement. Includes all necessary wire and breakers to meet electrical code.'

Option B: 'Install (1) 30-amp double-pole breaker and 50ft of 10/3 NM-B cable to a NEMA 6-30R receptacle. Excludes any drywall cutting, patching, or painting required for wire routing.'

Critique these options to determi