Multiple Choice

You are starting a project where your actual upfront costs for permits, material deposits, and equipment staging total $6,000. However, the client's contract strictly limits the initial 'Down Payment' to $2,500. To ensure your business maintains a neutral cash position in Month 1, how should you apply the mobilization pricing strategy to your Schedule of Values?