You are tasked with developing a bid for a 'Fast-Track' renovation of a commercial office space. The client needs a contract signed immediately to secure their construction loan, but the electrical engineers have only completed 60% of the construction drawings. To create a professional and protective bid proposal for this specific challenge, which strategy should you employ to structure your pricing?