Multiple Choice

A contractor bid a warehouse lighting upgrade in March but did not buy the copper feeder cable until June. Labor finished exactly as budgeted, yet the final job showed a loss because the cable cost 20% more than the estimate. Which conclusion best explains the cause of the loss?