An electrical contractor analyzes a proposal from an overseas supplier offering bulk wire at a cost 20%20\% lower than local distributors, which would save the business $5,000. However, the contractor discovers that the products lack a UL listing and do not meet National Electrical Code (NEC) standards. By rejecting the supplier to avoid inspection failures and liability, the contractor is prioritizing the factor of ____ over competitive pricing.