Multiple Choice

An electrical contractor is bidding on a specialized residential automation project and must choose between two distributors for the necessary components:

  • Distributor A: Offers the lowest Competitive Pricing, but provides no support. The contractor estimates they will need to spend 10 hours of their own time researching NEC code requirements and component compatibility for the project.
  • Distributor B: Costs $800 more than Distributor A for the same materials but offers expert Technical Assistance, including a specialist who will verify the code compliance and compatibility of the entire order before it is shipped.

If the contractor values their own administrative time at $100 per hour, which of the following is the most logically sound evaluation of the best selection factor to prioritize in this scenario?