An electrical contractor evaluates the final outcomes of several lighting jobs and discovers they consistently failed to protect the gross margin. The actual cost records show that the crews executed the labor plan and material plan perfectly without any scope changes. Applying the estimate-actual-result loop, the contractor judges that the financial failure occurred before the work even began, meaning they must fundamentally adjust their ________ to make future lighting jobs profitable.