Multiple Choice

An electrical contractor finds that the specified 200200-amp main breakers are backordered. They find a different UL-listed brand that meets all NEC requirements and performance specs. To avoid delays, the contractor installs the alternative brand immediately without getting a signature from the project architect. According to the 'Approved Substitution Process', what is the most likely consequence of this action?