Multiple Choice

An electrical contractor has finished the 'rough-in' conduit and wire-pull phase for an office renovation. This phase is assigned a value of $12,000 in the project's Schedule of Values (SOV). According to the principles of 'front-loading', how should the contractor handle the progress billing for this completed work?