An electrical contractor submits the first progress billing on a commercial project. The Schedule of Values lists rough-in conduit and wire-pull at $18,000. Site records confirm 100% of that work is complete, and the contractor provides material invoices and labor timesheets totaling $17,600 to support the full $18,000 billing amount. A project owner's auditor reviews the submission and determines that the $18,000 claim is ____, because the billed amount is fully supported by documented costs and reflects work that has actually been performed.