Multiple Choice

An electrical contractor includes the following clause in a residential rewiring contract: 'A $3,000 deposit is required to cover the costs of the electrical permit, rough-in materials, and specialized lighting fixtures.' When the contractor calls to collect the deposit five days before the scheduled start, the customer claims they aren't required to pay until the materials arrive on-site. Why is this contract language analytically insufficient for protecting the contractor's mobilization schedule?