Multiple Choice

An electrical contractor is analyzing a post-project report for a conduit installation job. The project used standard labor units that assume a '50/50' split—meaning 50% of the labor unit is allocated for physical installation and 50% is allocated for support activities.

The report shows that while the crew's 'Material Installation' speed (the physical 50%) was exactly on target, the total project hours exceeded the estimate by 15%. The analysis identifies two specific factors:

  1. The crew had