You are investigating why a recent conduit installation project exceeded its estimated labor budget. The field team worked efficiently during the actual installation and layout phases, and supervision was accounted for separately. However, you discover that site restrictions forced the electricians to walk 15 minutes each way to retrieve conduit from a remote staging area multiple times a day. By breaking down the components of a standard labor unit, you determine the cost overrun occurred because this logistical issue exceeded the standard allowance for normal ________.